Fronterra Neighborhood Park
CIP LogoFast Facts
Total Project Budget: $3.9 million
Status: Completed
Construction Began: December 4, 2014
Opened: August 25, 2015
Located at: 10020 Joplin Street, Commerce City, CO 80022

Park Theme
The 19.8-acre park features an active, nature-inspired theme with dedicated play areas, open space and walking/jogging path. The site is located in between Stuart Middle School and Second Creek Elementary School, in the Fronterra Park neighborhood. 

Park Features
  • Hillside Slide
  • Small skate area
  • Two graded playfields
  • Picnic areas with shelters
  • Playgrounds
  • Walking/Jogging trails
  • Sustainable landscaping
  • Low-level safety lighting
  • Restrooms
  • Multi-use hard court for informal/drop-in basketball,hopscotch, roller hockey, etc.
  • Fitness stations and equipment
  • ADA accessible
  • Wide range of activities for all ages

Outreach & Engagement
Commerce City asked the community to vote on an overall concept and preferred optional elements. After three public meetings and online input, the community voted on a nature-inspired, active concept and a hillside slide. The project team refined the design to reflect the community’s input while staying within schedule and budget. The final design was presented to City Council on June 16, 2014.

See the June 11 meeting summary and presentation.
See the May 21 meeting summary.
See the May 1 meeting summary.

  • Designer: DHM Design
  • Contractor: Golden Triangle Construction (GTC)